Project Details
Client: | Ministry of Transportation (MTO) |
---|---|
Location: | 2014-4029 HWY. 417 – From Anderson Road Easterly to Limoges Road 25 km |
Timeframe: | March 2015 – September 2017 |
Value: | $60M |
Project Type: | Bridge Replacement, Pavement Rehabilitation, Grading, Drainage, Granular Base, Hot Mix Paving, Electrical and Structural |
Consultant: | McIntosh Perry |
Partners: |
|
Project Description
- Rehabilitate 8th line Overpass – Piperville (175 m) and 7th Line Overpass- Leitrim (235 m)
- Protection System
- Jacking of superstructure
- Concrete overlay
- Remove existing culvert at Shaw’s Creek and install twin box culvert 3000mm x 2400mm Precast Concrete box culvert (208m)
- Construction of two new Bridges (120 m & 160 m) at Bear Brook and highway realignment :
- Cofferdams
- H-Piles
- Rock Points
- Structural Steel Girders
- Demolition of two existing bridges at Bear Brook
- 50km Pavement rehabilitation: 330,000 m2 of cold in-place (CIREAM) and 170,000 tonnes of asphalt
- Rigid Expanded Polystyrene Embankment fill
Services Provided
Grading, Drainage, Granular Base, Hot Mix Paving, Electrical and Structural

